Works will commence for the A1(M)Hatfield Tunnel Refurbishment Project on the evening of Wednesday 3rd June 2009, when the contractors will start to install traffic management. The traffic management installation will be completed by Friday 5th June (am) and there will be a mandatory 40mph speed restriction in place throughout the duration of the works.

Phase 1 Works - Traffic will be in 3 narrow lanes both directions (as is currently). Duration of works approximately 7 weeks.

Phase 2 Works - Traffic will be in 2 lanes (contraflow) in each direction in the southbound tunnel. Duration of works approximately 9 months.

Phase 3 Works - Traffic will be in 2 lanes (contraflow) in each direction in the northbound tunnel. Duration of works approximately 9 month.

 

 

Phase 4 - Traffic will return back to 3 narrow lanes in each direction in each tunnel bore. Duration of works approximately 2 weeks.

We will post further information as we receive it.